Croatian Motorways "Makeover" to Total 263 Million Kuna from Own Funds

May the 4th, 2022 - Croatian Motorways (HAC/Hrvatske autoceste) is set to spend a massive amount on a ''makeover'' of sorts. Here's precisely how a total of 263 million kuna will be spent.

As Poslovni Dnevnik/Marija Brnic writes, Croatian Motorways will soon get to work on the demolition of Motel Rastovica on the A3 Bregana-Zagreb-Lipovac motorway. A job tender worth around three million kuna is now underway, but, as was confirmed by Croatian Motorways, no new content will be built on the site after the removal of that facility.

What are set to be removed are old and neglected motel and bungalow facilities that have been out of function for a long time now, are in quite a dilapidated condition and, according to Croatian Motorways, pose a danger to the environment and the safety of resort users.

Their removal of Motel Rastovica and its accompanying facilities is part of a wider project of revitalisation and arrangement of the network of rest/stop areas and accompanying service facilities along the entire A3 route, and the construction of a new facility at a specific location is not currently planned, because, according to Croatian Motorways, there is already a very modern fuel station with a shop and a restaurant at that location, which provides a high level of service quality for all road passengers.

The A3 motorway is mostly an old motorway route where the rest area network requires general reconstruction, and in addition to restoring the rest area, new rest plateaus are being built in that direction, existing rest areas are being abolished and dilapidated and devastated ancillary service facilities are being removed. HAC, based on the projection of the optimal layout of rest areas with regard to their type and mutual distance.

The revitalisation project includes about 30 rest areas, and the investment, which Croatian Motorways is financing from its own sources and intends to complete by June 2026, is worth a total of 263 million kuna.

This year, the project will see the completion of the construction of the Crnec rest area on the Ivanja Reka-Jezevo section, the general reconstruction of the Jezevo-south rest area and the Nova Gradiska-Dragalic-north rest area, as well as the reconstruction of the motorway and removal of the Jezevo-north rest area connection.