More Than 1000 Workers Currently at Peljesac Bridge and Access Roads

By 20 September 2021

September the 20th, 2021 - Works at the Peljesac bridge site, Croatia's most important stragetic project, are going at full speed as 1000 workers are busy finishing things off and dealing with the access roads.

As Poslovni Dnevnik writes, the Peljesac bridge and access road construction site is as busy as ever. More than 1,000 workers are currently employed on this largest construction site in the Republic of Croatia. More precisely, according to Hrvatske ceste (Croatian roads), Peljesac bridge and its access roads are being built by a total of 1,098 workers at this moment in time, and when technical and support staff are added, there will be a total of 1,277 people on the ground on site and in the nearby Mali Ston Bay, as reported by Vecernji list.

On the access roads themselves, (more precisely on the Duboka - Sparagovici section) work was being carried out on the wide excavation of the route all the way to the Kamenica tunnel. Between the Dumanja Jaruga bridges (I and II) and the Debeli brijeg tunnel, work is currently being done on the construction of an external drainage system, and on the Dumanja Jaruga I bridge, the construction of columns as well as the first segment of the span structure on pillar S1 has now been completed.

On the Dumanja Jaruga II bridge, two segments of the span structure were constructed with the help of a cage, and the foundation was concreted on the S1 pillar. At the Zaradeza junction, excavation works are underway for the future Zaradeza traffic control centre, where walls, horizontal and vertical circles are currently being built. In the Debeli Brijeg tunnel (1424 metres in length), which was breached back in December, works on the construction of waterproofing, reprofiling and sub-concrete are continuing. A total of 296 workers are engaged on this section of the access roads, of which 61 are technical staff.

On the Ston bypass and the Sparagovici - Papratno - Doli road section, among other things, all segments have been drawn up on the Prapratno viaduct. Works on the steel structure and AKZ are also now in progress. The excavation of the Polakovica tunnel (1242 metres) has been completed, and a wide full profile excavation is now being carried out. The Supava tunnel (1290 metres) also now breaks through on two sides (and entrance and an exit).

On the Ston bridge (485 metres), reinforced concrete works on the head of the S5 pillar have now been completed. Reinforced concrete works on the construction of the pillar of the S3 pillar are in progress. The reinforced concrete foundation of the S4 staircase has been completed and reinforced concrete works on the construction of the pillar of the S4 staircase are in progress. Works on the head of the pillar of the S2 pillar and reinforced concrete works on the abutments of the Ston U1 and U7 bridges are in progress and the second phase of the wall and wings of the U7 abutment has been completed. A total of 330 workers are engaged in various jobs on the Peljesac bridge construction site, along with 33 members of the technical and administrative staff.