Green Action and Green Istria's Lawsuit Over Plomin 1 Environmental Permit Rejected

By 5 March 2021
Green Action and Green Istria's Lawsuit Over Plomin 1 Environmental Permit Rejected
© Općina Kršan

ZAGREB, 5 March, 2021 - The Administrative Court in Rijeka issued a non-final verdict and rejected the claim of the Green Action and Green Istria associations, which sought to revoke the environmental permit for the coal-fired Plomin 1 thermal power plant issued by the Economy and Sustainable Development Ministry.

As the court reported, when announcing the verdict, which can be appealed against to the High Administrative Court, it was said that the administrative dispute did not decide whether the planned operation of Plomin 1 was inconsistent with the strategies and plans of the HEP power company and the Croatian government.

According to the explanation, those issues are not subject to consideration when determining the conditions for issuing an environmental permit. The court determined that the decision was made in accordance with the relevant regulations on the issuance of environmental permits for existing plants. It also established that the Ministry of Economy and Sustainable Development correctly and fully established the decisive facts in the administrative procedure, with valid application of substantive law.

Bernard Ivčić of the Green Action said on Friday that the associations would, after receiving the explanation of the verdict, consider the possibilities and probably file an appeal.